Skip to main content
Macroeconomics
My Course
Learn
Exam Prep
AI Tutor
Study Guides
Flashcards
Explore
My Course
Learn
Exam Prep
AI Tutor
Study Guides
Flashcards
Explore
Back
14. The Financial System
Download worksheet
Problem 1
Problem 2
Problem 3
Problem 4
Problem 5
Problem 6
Problem 7
Problem 8
Problem 9
Problem 10
Problem 11
Problem 12
Problem 13
Problem 14
Problem 15
14. The Financial System
Download worksheet
Practice
Summary
Previous
7 of 15
Next
13. The Financial System / Market for Loanable Funds / Problem 7
Problem 7
A firm is evaluating two projects: Project A with a 7% return and Project B with a 4% return. If the interest rate is 5%, which project should the firm choose?
A
Project B, because it has a lower return.
B
Neither, because both returns are below the interest rate.
C
Both, because they both have positive returns.
D
Project A, because its return exceeds the interest rate.